Method Statement for Recast Segment

1. INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT The purpose of this procedure is to define the method to recast the typical segment that need to be carried out on the Long Line and Short Line Typical Moulds. This procedure shall be read together with the Method Statement of Precast Segment Production - Long Line Typical Mould, ref. UMRTL1-CP2-CSYD-CWS-MST-00065 and Method Statement of Precast Segment Production - Short Line Typical mould, ref.

Method Statement for Rebar Cut & Bend Works

1. INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT The purpose of this procedure is cut and bend rebar works related to the production of precast segments composing the viaducts of HCMC Line1 – Metro Project. 1.2 PROJECT DESCRIPTION Ho Chi Minh City Urban Railway Construction Project – Ben Thanh – Suoi Tien section (Line 1), contract Package 2 consists of approximately 12 km long of elevated viaduct structures, erected by span-by-span Method.